Stampede Solar Hybrid (67762_STMPB)

Stampede Solar Hybrid is a 72.2 MW battery interconnection project in Hopkins, Texas with a current status of operational.

72.2 MWCapacity
OperationalStatus
ERCOMarket
BatteryTechnology

Project facts

Canonical nameStampede Solar Hybrid
Queue ID67762_STMPB
Statusoperational
Source status(OP) Operating
MarketERCO
TechnologyBattery
Capacity72.2 MW
StateTexas
CountyHopkins
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date2024-10-01
Withdrawn date—
Developer—
Utility / transmission ownerStampede Solar Project LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—operationalhigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-11

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata