Starlight Solar (27INR0105)

Starlight Solar is a 130.7 MW solar interconnection project in Mills, Texas with a current status of operational. It is proposed to connect at tap the 138 kV Goldthwaite (#7070) – San Saba Switch (#77074) .

130.7 MWCapacity
OperationalStatus
MillsMarket
SolarTechnology

Project facts

Canonical nameStarlight Solar
Queue ID27INR0105
Statusoperational
Source statusSS Completed, FIS Started, IA
MarketMills
TechnologySolar
Capacity130.7 MW
StateTexas
CountyMills
Point of interconnectiontap the 138 kV Goldthwaite (#7070) – San Saba Switch (#77074)
Requested (queue) date2024-02-27
Proposed in-service date
Operational date2030-05-09
Withdrawn date
DeveloperMills Tx Solar LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.