Starr Nelson 115 Substation is a 199.0 MW gas interconnection project in Delta County,, Colorado with a current status of withdrawn. It is proposed to connect at Starr Nelson 115 Substation.

199.0 MWCapacity
WithdrawnStatus
COMarket
GasTechnology

Project facts

Canonical nameStarr Nelson 115 Substation
Queue IDGI-CS-2025-27
Statuswithdrawn
Source statusWITHDRAWN
MarketCO
TechnologyGas
Capacity199.0 MW
StateColorado
CountyDelta County,
Point of interconnectionStarr Nelson 115 Substation
Requested (queue) date2025-10-03
Proposed in-service date2029-04-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerTSGT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; tristate-oasis. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-15statusoperationalwithdrawnhigh
2026-09-15operational_date2029-04-01—medium
2026-09-15proposed_online_date—2029-04-01medium
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata