Stone Lake - Gardner Park 345.0kV (J3975)

Stone Lake - Gardner Park 345.0kV is a 416.5 MW solar interconnection project in Rusk, Wisconsin with a current status of operational. It is proposed to connect at Stone Lake - Gardner Park 345.0kV.

416.5 MWCapacity
OperationalStatus
Market
SolarTechnology

Project facts

Canonical nameStone Lake - Gardner Park 345.0kV
Queue IDJ3975
Statusoperational
Source statusActive
Market
TechnologySolar
Capacity416.5 MW
StateWisconsin
CountyRusk
Point of interconnectionStone Lake - Gardner Park 345.0kV
Requested (queue) date2025-03-10
Proposed in-service date2030-02-20
Operational date2030-02-20
Withdrawn date
Developer
Utility / transmission ownerAMERICAN TRANSMISSION COMPANY

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata