Streamfield (1117)

Streamfield is a 202.4 MW battery interconnection project in Hampden, Massachusetts with a current status of withdrawn. It is proposed to connect at The proposed POI is Buck Pond 115 kV substation, the alternative POI is to build a new substation next to Buck pond 115 kV in the north side by breaking Line 1657.

202.4 MWCapacity
WithdrawnStatus
WMAMarket
BatteryTechnology

Project facts

Canonical nameStreamfield
Queue ID1117
Statuswithdrawn
Source statusW
MarketWMA
TechnologyBattery
Capacity202.4 MW
StateMassachusetts
CountyHampden
Point of interconnectionThe proposed POI is Buck Pond 115 kV substation, the alternative POI is to build a new substation next to Buck pond 115 kV in the north side by breaking Line 1657
Requested (queue) date2021-04-15
Proposed in-service date2027-05-31
Operational date
Withdrawn date2025-04-28
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.