Stryker 22, L.L.C. (61891_EDGRD)

Stryker 22, L.L.C. is a 19.8 MW battery interconnection project in Warren, New Jersey with a current status of operational.

19.8 MWCapacity
OperationalStatus
PJMMarket
BatteryTechnology

Project facts

Canonical nameStryker 22, L.L.C.
Queue ID61891_EDGRD
Statusoperational
Source status(OP) Operating
MarketPJM
TechnologyBattery
Capacity19.8 MW
StateNew Jersey
CountyWarren
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date2018-12-01
Withdrawn date—
Developer—
Utility / transmission ownerStryker 22, L.L.C.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—operationalhigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata