Summit Ridge Project (G98-01)
Summit Ridge Project is a 75.0 MW wind interconnection project in Wasco, Oregon with a current status of withdrawn. It is proposed to connect at Big Eddy–DeMoss 115 kV line 8-9 miles east of Big Eddy.
75.0 MWCapacity
WithdrawnStatus
ORMarket
WindTechnology
Project facts
| Canonical name | Summit Ridge Project |
|---|---|
| Queue ID | G98-01 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | OR |
| Technology | Wind |
| Capacity | 75.0 MW |
| State | Oregon |
| County | Wasco |
| Point of interconnection | Big Eddy–DeMoss 115 kV line 8-9 miles east of Big Eddy |
| Requested (queue) date | 2002-04-05 |
| Proposed in-service date | 2003-10-31 |
| Operational date | — |
| Withdrawn date | — |
| Developer | Seawest Windpower, Inc. |
| Utility / transmission owner | Bonneville Power Administration |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata