SW Minot is a 4.9 MW wind interconnection project in Max, North Dakota with a current status of active. It is proposed to connect at SW Minot.
4.9 MWCapacity
ActiveStatus
NDMarket
WindTechnology
Project facts
| Canonical name | SW Minot |
|---|---|
| Queue ID | GEN-2025-GR3 |
| Status | active |
| Source status | SPECIAL STUDY |
| Market | ND |
| Technology | Wind |
| Capacity | 4.9 MW |
| State | North Dakota |
| County | Max |
| Point of interconnection | SW Minot |
| Requested (queue) date | 2025-10-06 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | WAPA/BEPC/HCPD Integrated System |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | active | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.