Symphony BESS (26INR0466)

Symphony BESS is a 612.0 MW other interconnection project in Austin, Texas with a current status of operational. It is proposed to connect at 46220 PETERS.

612.0 MWCapacity
OperationalStatus
AustinMarket
OtherTechnology

Project facts

Canonical nameSymphony BESS
Queue ID26INR0466
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketAustin
TechnologyOther
Capacity612.0 MW
StateTexas
CountyAustin
Point of interconnection46220 PETERS
Requested (queue) date2025-02-14
Proposed in-service date
Operational date2028-07-01
Withdrawn date
DeveloperSymphony BESS, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.