Sypert Branch Solar Project (24INR0070)
Sypert Branch Solar Project is a 261.1 MW solar interconnection project in Milam, Texas with a current status of operational. It is proposed to connect at Tap 345kV #3751 Scooter Switch - #3687 Bell County East Switch Ckt 2.
261.1 MWCapacity
OperationalStatus
MilamMarket
SolarTechnology
Project facts
| Canonical name | Sypert Branch Solar Project |
|---|---|
| Queue ID | 24INR0070 |
| Status | operational |
| Source status | SS Completed, FIS Completed, IA |
| Market | Milam |
| Technology | Solar |
| Capacity | 261.1 MW |
| State | Texas |
| County | Milam |
| Point of interconnection | Tap 345kV #3751 Scooter Switch - #3687 Bell County East Switch Ckt 2 |
| Requested (queue) date | 2021-09-21 |
| Proposed in-service date | — |
| Operational date | 2026-04-30 |
| Withdrawn date | — |
| Developer | Sypert Branch Solar LLC |
| Utility / transmission owner | ERCOT |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.