t (915467)

t is a 61.2 MW solar interconnection project in Gilchrist, Florida with a current status of withdrawn. It is proposed to connect at Bell Tap.

61.2 MWCapacity
WithdrawnStatus
FLMarket
SolarTechnology

Project facts

Canonical namet
Queue ID915467
Statuswithdrawn
Source statusWithdrawn
MarketFL
TechnologySolar
Capacity61.2 MW
StateFlorida
CountyGilchrist
Point of interconnectionBell Tap
Requested (queue) date2023-09-15
Proposed in-service date2028-06-01
Operational date
Withdrawn date
DeveloperT and M Solar
Utility / transmission ownerDuke Energy Progress

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: duke-def-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata