Tap Amarillo South – Swisher County 230kV (GEN-2011-036)

Tap Amarillo South – Swisher County 230kV is a 270.0 MW wind interconnection project in Swisher County, Texas with a current status of withdrawn. It is proposed to connect at Tap Amarillo South – Swisher County 230kV.

270.0 MWCapacity
WithdrawnStatus
TXMarket
WindTechnology

Project facts

Canonical nameTap Amarillo South – Swisher County 230kV
Queue IDGEN-2011-036
Statuswithdrawn
Source statusWITHDRAWN
MarketTX
TechnologyWind
Capacity270.0 MW
StateTexas
CountySwisher County
Point of interconnectionTap Amarillo South – Swisher County 230kV
Requested (queue) date2011-07-01
Proposed in-service date
Operational date
Withdrawn date2011-10-03
Developer
Utility / transmission ownerSPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.