TGDV#2 (399)

TGDV#2 is a 60.7 MW gas interconnection project in Churchill, Nevada with a current status of withdrawn. It is proposed to connect at Control Substation 115kV bus.

60.7 MWCapacity
WithdrawnStatus
Market
GasTechnology

Project facts

Canonical nameTGDV#2
Queue ID399
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologyGas
Capacity60.7 MW
StateNevada
CountyChurchill
Point of interconnectionControl Substation 115kV bus
Requested (queue) date2008-05-29
Proposed in-service date
Operational date
Withdrawn date2011-03-22
Developer
Utility / transmission ownerSCE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.