Third Coast BESS (23INR0361)

Third Coast BESS is a 102.8 MW other interconnection project in Jackson, Texas with a current status of operational. It is proposed to connect at 8125 Lolita substation 138kV.

102.8 MWCapacity
OperationalStatus
JacksonMarket
OtherTechnology

Project facts

Canonical nameThird Coast BESS
Queue ID23INR0361
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketJackson
TechnologyOther
Capacity102.8 MW
StateTexas
CountyJackson
Point of interconnection8125 Lolita substation 138kV
Requested (queue) date2021-08-24
Proposed in-service date
Operational date2027-06-15
Withdrawn date
DeveloperThird Coast BESS LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.