Third Coast BESS (23INR0361)
Third Coast BESS is a 102.8 MW other interconnection project in Jackson, Texas with a current status of operational. It is proposed to connect at 8125 Lolita substation 138kV.
102.8 MWCapacity
OperationalStatus
JacksonMarket
OtherTechnology
Project facts
| Canonical name | Third Coast BESS |
|---|---|
| Queue ID | 23INR0361 |
| Status | operational |
| Source status | SS Completed, FIS Completed, IA |
| Market | Jackson |
| Technology | Other |
| Capacity | 102.8 MW |
| State | Texas |
| County | Jackson |
| Point of interconnection | 8125 Lolita substation 138kV |
| Requested (queue) date | 2021-08-24 |
| Proposed in-service date | — |
| Operational date | 2027-06-15 |
| Withdrawn date | — |
| Developer | Third Coast BESS LLC |
| Utility / transmission owner | ERCOT |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata