Tie 69 kV Substation (GEN-2023-121)

Tie 69 kV Substation is a 50.0 MW solar interconnection project in Cowley, Kansas with a current status of withdrawn. It is proposed to connect at Tie 69 kV Substation.

50.0 MWCapacity
WithdrawnStatus
KSMarket
SolarTechnology

Project facts

Canonical nameTie 69 kV Substation
Queue IDGEN-2023-121
Statuswithdrawn
Source statusWITHDRAWN
MarketKS
TechnologySolar
Capacity50.0 MW
StateKansas
CountyCowley
Point of interconnectionTie 69 kV Substation
Requested (queue) date2023-10-02
Proposed in-service date2030-12-31
Operational date
Withdrawn date2024-03-22
Developer
Utility / transmission ownerGridLiance

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata