TImmerman Power Plant (25INR0223)

TImmerman Power Plant is a 188.4 MW gas interconnection project with a current status of operational. It is proposed to connect at Clear Springs (#7050) and L_Hornsb8_1Y (#7047).

188.4 MWCapacity
OperationalStatus
ERCOTMarket
GasTechnology

Project facts

Canonical nameTImmerman Power Plant
Queue ID25INR0223
Statusoperational
Source statusoperational
MarketERCOT
TechnologyGas
Capacity188.4 MW
State
County
Point of interconnectionClear Springs (#7050) and L_Hornsb8_1Y (#7047)
Requested (queue) date2022-09-27
Proposed in-service date2025-08-12
Operational date2025-08-14
Withdrawn date
DeveloperLower Colorado River Authority
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata