TN Queue Project 588 — Gas in Shelby, Tennessee

TN Queue Project 588 — Gas in Shelby, Tennessee is a 198.0 MW gas interconnection project in Shelby, Tennessee with a current status of active. It is proposed to connect at Allen 161-kV substation.

198.0 MWCapacity
ActiveStatus
TNMarket
GasTechnology

Project facts

Canonical nameTN Queue Project 588 — Gas in Shelby, Tennessee
Queue ID588
Statusactive
Source statusFacilities Study
MarketTN
TechnologyGas
Capacity198.0 MW
StateTennessee
CountyShelby
Point of interconnectionAllen 161-kV substation
Requested (queue) date2023-11-03
Proposed in-service date2024-10-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerTennessee Valley Authority

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-24poi_nameL5396, Str 8 - Allen CCPAllen 161-kV substationlow
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: tva-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.