TN Queue Project ERAS-003 — Gas in Humpreys, Tennessee
TN Queue Project ERAS-003 — Gas in Humpreys, Tennessee is a 312.0 MW gas interconnection project in Humpreys, Tennessee with a current status of active. It is proposed to connect at Johnsonville FP.
312.0 MWCapacity
ActiveStatus
TNMarket
GasTechnology
Project facts
| Canonical name | TN Queue Project ERAS-003 — Gas in Humpreys, Tennessee |
|---|---|
| Queue ID | ERAS-003 |
| Status | active |
| Source status | Deficiency Check |
| Market | TN |
| Technology | Gas |
| Capacity | 312.0 MW |
| State | Tennessee |
| County | Humpreys |
| Point of interconnection | Johnsonville FP |
| Requested (queue) date | 2026-06-05 |
| Proposed in-service date | 2026-09-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Tennessee Valley Authority |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-24 | new_project | — | active | high |
Explore related data
Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27
Provenance: tva-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.