TN Queue Project RSC26-008 — Battery in Hawkins, Tennessee

TN Queue Project RSC26-008 — Battery in Hawkins, Tennessee is a 400.0 MW battery interconnection project in Hawkins, Tennessee with a current status of active. It is proposed to connect at Phipps Bend 500 kV substation.

400.0 MWCapacity
ActiveStatus
TNMarket
BatteryTechnology

Project facts

Canonical nameTN Queue Project RSC26-008 — Battery in Hawkins, Tennessee
Queue IDRSC26-008
Statusactive
Source statusDeficiency Check
MarketTN
TechnologyBattery
Capacity400.0 MW
StateTennessee
CountyHawkins
Point of interconnectionPhipps Bend 500 kV substation
Requested (queue) date2026-08-10
Proposed in-service date2031-05-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerTennessee Valley Authority

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-24new_project—activehigh

Explore related data

Source last checked2026-11-23
Data last materially changed2026-11-23
Page data generated2026-11-26

Provenance: tva-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata