TOCE GA Solar 4 (GI-189)

TOCE GA Solar 4 is a 325.0 MW solar+battery interconnection project in Jefferson County, Georgia with a current status of active. It is proposed to connect at Wadley – Waynesboro TL line tap.

325.0 MWCapacity
ActiveStatus
GAMarket
Solar+BatteryTechnology

Project facts

Canonical nameTOCE GA Solar 4
Queue IDGI-189
Statusactive
Source statusFull NTP
MarketGA
TechnologySolar+Battery
Capacity325.0 MW
StateGeorgia
CountyJefferson County
Point of interconnectionWadley – Waynesboro TL line tap
Requested (queue) date2024-01-08
Proposed in-service date2027-02-28
Operational date
Withdrawn date
Developer
Utility / transmission ownerGeorgia Transmission

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: gtc-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata