Towanda 115kV (V3-018)

Towanda 115kV is a 75.0 MW wind interconnection project in Bradford, Pennsylvania with a current status of withdrawn.

75.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameTowanda 115kV
Queue IDV3-018
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity75.0 MW
StatePennsylvania
CountyBradford
Point of interconnection
Requested (queue) date2009-08-24
Proposed in-service date2012-12-31
Operational date
Withdrawn date2010-09-01
Developer
Utility / transmission ownerPENELEC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-28

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.