Troy Battery Storage (AH1-565)

Troy Battery Storage is a 250.0 MW battery interconnection project in Wood, Ohio with a current status of withdrawn. It is proposed to connect at Lemoyne 345kV.

250.0 MWCapacity
WithdrawnStatus
PJMMarket
BatteryTechnology

Project facts

Canonical nameTroy Battery Storage
Queue IDAH1-565
Statuswithdrawn
Source statuswithdrawn
MarketPJM
TechnologyBattery
Capacity250.0 MW
StateOhio
CountyWood
Point of interconnectionLemoyne 345kV
Requested (queue) date2021-09-10
Proposed in-service date2025-06-01
Operational date
Withdrawn date2025-05-07
DeveloperTroy Energy LLC
Utility / transmission ownerATSI

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.