Tucumcari - Norton 115 kV Line Tap (GEN-2023-095)

Tucumcari - Norton 115 kV Line Tap is a 850.0 MW solar interconnection project in Quay, New Mexico with a current status of withdrawn. It is proposed to connect at Tucumcari - Norton 115 kV Line Tap.

850.0 MWCapacity
WithdrawnStatus
NMMarket
SolarTechnology

Project facts

Canonical nameTucumcari - Norton 115 kV Line Tap
Queue IDGEN-2023-095
Statuswithdrawn
Source statusWITHDRAWN
MarketNM
TechnologySolar
Capacity850.0 MW
StateNew Mexico
CountyQuay
Point of interconnectionTucumcari - Norton 115 kV Line Tap
Requested (queue) date2023-10-02
Proposed in-service date2028-12-01
Operational date
Withdrawn date2024-01-16
Developer
Utility / transmission ownerSPS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.