TWINKLETOWN (S1134)
TWINKLETOWN is a 100.0 MW battery interconnection project in DeSoto, Mississippi with a current status of operational. It is proposed to connect at TWINKLETOWN.
100.0 MWCapacity
OperationalStatus
—Market
BatteryTechnology
Project facts
| Canonical name | TWINKLETOWN |
|---|---|
| Queue ID | S1134 |
| Status | operational |
| Source status | Active |
| Market | — |
| Technology | Battery |
| Capacity | 100.0 MW |
| State | Mississippi |
| County | DeSoto |
| Point of interconnection | TWINKLETOWN |
| Requested (queue) date | 2025-12-24 |
| Proposed in-service date | 2028-01-03 |
| Operational date | 2028-01-03 |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | ENTERGY ARKANSAS |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-29 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28
Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.