Two Rivers Solar (GI-162)

Two Rivers Solar is a 102.0 MW solar+battery interconnection project in Camden County, Georgia with a current status of active. It is proposed to connect at Homeland - Kingsland 115 kV line.

102.0 MWCapacity
ActiveStatus
GAMarket
Solar+BatteryTechnology

Project facts

Canonical nameTwo Rivers Solar
Queue IDGI-162
Statusactive
Source statusFacilities Study
MarketGA
TechnologySolar+Battery
Capacity102.0 MW
StateGeorgia
CountyCamden County
Point of interconnectionHomeland - Kingsland 115 kV line
Requested (queue) date2022-03-16
Proposed in-service date2024-10-16
Operational date
Withdrawn date
Developer
Utility / transmission ownerGeorgia Transmission

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: gtc-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata