TX Fort Worth 5200 Gold Spike Drive (67058_19599)

TX Fort Worth 5200 Gold Spike Drive is a 4.0 MW solar interconnection project in Tarrant, Texas with a current status of operational.

4.0 MWCapacity
OperationalStatus
ERCOMarket
SolarTechnology

Project facts

Canonical nameTX Fort Worth 5200 Gold Spike Drive
Queue ID67058_19599
Statusoperational
Source status(OP) Operating
MarketERCO
TechnologySolar
Capacity4.0 MW
StateTexas
CountyTarrant
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date2025-02-01
Withdrawn date—
Developer—
Utility / transmission ownerCatalyze Fort Worth 5200 Gold Spike Drive Microgrid, LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—operationalhigh

Explore related data

Source last checked2026-11-01
Data last materially changed2026-11-01
Page data generated2026-11-26

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.