UT Queue Project 785 — Solar+Battery in Juab, Utah

UT Queue Project 785 — Solar+Battery in Juab, Utah is a 199.0 MW solar+battery interconnection project in Juab, Utah with a current status of active. It is proposed to connect at 345kV Mona Substation.

199.0 MWCapacity
ActiveStatus
UTMarket
Solar+BatteryTechnology

Project facts

Canonical nameUT Queue Project 785 — Solar+Battery in Juab, Utah
Queue ID785
Statusactive
Source statusActive
MarketUT
TechnologySolar+Battery
Capacity199.0 MW
StateUtah
CountyJuab
Point of interconnection345kV Mona Substation
Requested (queue) date2025-04-14
Proposed in-service date2027-09-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerIdaho Power Company

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-24phaseFSRDGIAlow
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: idahopower-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata