Vast Sands Power I (TEF -Due Diligence) (28INR0105)

Vast Sands Power I (TEF -Due Diligence) is a 440.0 MW gas interconnection project in Ward, Texas with a current status of operational. It is proposed to connect at Tap 345kV 11010 Wolf Switch - 11188 Quarry Field Switch Ckt 2 .

440.0 MWCapacity
OperationalStatus
WardMarket
GasTechnology

Project facts

Canonical nameVast Sands Power I (TEF -Due Diligence)
Queue ID28INR0105
Statusoperational
Source statusSS Completed, FIS Started, IA
MarketWard
TechnologyGas
Capacity440.0 MW
StateTexas
CountyWard
Point of interconnectionTap 345kV 11010 Wolf Switch - 11188 Quarry Field Switch Ckt 2
Requested (queue) date2024-07-22
Proposed in-service date
Operational date2028-05-01
Withdrawn date
DeveloperPermian Power I LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-28

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.