Velado Solar SLF (27INR0373)

Velado Solar SLF is a 115.2 MW solar interconnection project in Dimmit, Texas with a current status of operational. It is proposed to connect at Tap 138kV 78281 Dimmit - 8274 Conoco Chittam .

115.2 MWCapacity
OperationalStatus
DimmitMarket
SolarTechnology

Project facts

Canonical nameVelado Solar SLF
Queue ID27INR0373
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketDimmit
TechnologySolar
Capacity115.2 MW
StateTexas
CountyDimmit
Point of interconnectionTap 138kV 78281 Dimmit - 8274 Conoco Chittam
Requested (queue) date2024-11-19
Proposed in-service date
Operational date2028-09-14
Withdrawn date
DeveloperVelado Solar, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.