Velociraptor BESS I (27INR0493)

Velociraptor BESS I is a 246.0 MW other interconnection project in Ector, Texas with a current status of operational. It is proposed to connect at 10012 METEOR_5 Substation 345kV.

246.0 MWCapacity
OperationalStatus
EctorMarket
OtherTechnology

Project facts

Canonical nameVelociraptor BESS I
Queue ID27INR0493
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketEctor
TechnologyOther
Capacity246.0 MW
StateTexas
CountyEctor
Point of interconnection10012 METEOR_5 Substation 345kV
Requested (queue) date2025-05-27
Proposed in-service date
Operational date2029-12-01
Withdrawn date
DeveloperGreyhound BESS 3 LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.