Velociraptor Solar I (22INR0218)

Velociraptor Solar I is a 241.7 MW solar interconnection project in Ector, Texas with a current status of operational. It is proposed to connect at #10012 METEOR 5 Substation 345kV.

241.7 MWCapacity
OperationalStatus
EctorMarket
SolarTechnology

Project facts

Canonical nameVelociraptor Solar I
Queue ID22INR0218
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketEctor
TechnologySolar
Capacity241.7 MW
StateTexas
CountyEctor
Point of interconnection#10012 METEOR 5 Substation 345kV
Requested (queue) date2019-05-14
Proposed in-service date
Operational date2029-12-01
Withdrawn date
DeveloperGreyhound Solar 3 LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.