WA Queue Project Q60 — Solar+Battery in Asotin, Washington

WA Queue Project Q60 — Solar+Battery in Asotin, Washington is a 150.0 MW solar+battery interconnection project in Asotin, Washington with a current status of withdrawn. It is proposed to connect at Dry Creek 230kV Station.

150.0 MWCapacity
WithdrawnStatus
WAMarket
Solar+BatteryTechnology

Project facts

Canonical nameWA Queue Project Q60 — Solar+Battery in Asotin, Washington
Queue IDQ60
Statuswithdrawn
Source statusWithdrawn
MarketWA
TechnologySolar+Battery
Capacity150.0 MW
StateWashington
CountyAsotin
Point of interconnectionDry Creek 230kV Station
Requested (queue) date
Proposed in-service date
Operational date
Withdrawn date
Developer
Utility / transmission ownerAvista Utilities

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: avista-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata