Asotin County, Washington — Interconnection Projects

The interXdata warehouse tracks 6 interconnection projects in Asotin, Washington, representing 1,160 MW of requested capacity.

6Total projects
0Active
0Operational
5Withdrawn
1,160 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Solar+Battery4660 MW
Solar1300 MW
Wind1200 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
WA Queue Project G0736 — Solar in Asotin, WashingtonG0736Solar300.0 MWwithdrawnAsotin, Washington
PACW Queue Project C3-029 — Solar+Battery in Asotin, WashingtonC3-029Solar+Battery200.0 MWwithdrawnAsotin, Washington
Horizon Wind Energy-WRidgeG79Wind200.0 MWwithdrawnAsotin, Washington
PACW Queue Project C2-41 — Solar+Battery in Asotin, WashingtonC2-41Solar+Battery160.0 MWwithdrawnAsotin, Washington
WA Queue Project Q60 — Solar+Battery in Asotin, WashingtonQ60Solar+Battery150.0 MWwithdrawnAsotin, Washington
West Queue Project 60 — Solar+Battery in Asotin, Washington60Solar+Battery150.0 MWsuspendedAsotin, Washington

Top developers

Developer (canonical)ProjectsCapacity
Wind Ridge Power Partners, LLC1200 MW

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: avista-oasis; bpa-oasis; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; pacificorp-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Get an alert when a new project is proposed in Asotin County.