Walnut Grove-Asahi 69 kV (AG1-406 - moved to TC1)

Walnut Grove-Asahi 69 kV is a 22.0 MW battery interconnection project in McLean, Kentucky with a current status of withdrawn.

22.0 MWCapacity
WithdrawnStatus
—Market
BatteryTechnology

Project facts

Canonical nameWalnut Grove-Asahi 69 kV
Queue IDAG1-406 - moved to TC1
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyBattery
Capacity22.0 MW
StateKentucky
CountyMcLean
Point of interconnection—
Requested (queue) date2020-09-30
Proposed in-service date2024-09-25
Operational date—
Withdrawn date2025-11-03
Developer—
Utility / transmission ownerEKPC

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.