Wang Solar SLF (20INR0106)

Wang Solar SLF is a 144.6 MW solar interconnection project in Falls, Texas with a current status of operational. It is proposed to connect at tap 345kV 3409 LakeCr1 - 3414 TempSS.

144.6 MWCapacity
OperationalStatus
FallsMarket
SolarTechnology

Project facts

Canonical nameWang Solar SLF
Queue ID20INR0106
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketFalls
TechnologySolar
Capacity144.6 MW
StateTexas
CountyFalls
Point of interconnectiontap 345kV 3409 LakeCr1 - 3414 TempSS
Requested (queue) date2018-06-14
Proposed in-service date
Operational date2026-03-31
Withdrawn date
DeveloperBT Yixin Solar, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-28

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata