Washington-Furnace Brook Tap 34.5 kV (AG2-189 - moved to TC2)

Washington-Furnace Brook Tap 34.5 kV is a 19.8 MW solar interconnection project in Warren, New Jersey with a current status of withdrawn.

19.8 MWCapacity
WithdrawnStatus
—Market
SolarTechnology

Project facts

Canonical nameWashington-Furnace Brook Tap 34.5 kV
Queue IDAG2-189 - moved to TC2
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologySolar
Capacity19.8 MW
StateNew Jersey
CountyWarren
Point of interconnection—
Requested (queue) date2021-02-27
Proposed in-service date2022-02-23
Operational date—
Withdrawn date2025-06-26
Developer—
Utility / transmission ownerJCPL

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.