WELLHEAD POWER SALADO (352)
WELLHEAD POWER SALADO is a 49.0 MW gas interconnection project in Stanislaus, California with a current status of withdrawn. It is proposed to connect at Salado Substation 115 kV.
49.0 MWCapacity
WithdrawnStatus
—Market
GasTechnology
Project facts
| Canonical name | WELLHEAD POWER SALADO |
|---|---|
| Queue ID | 352 |
| Status | withdrawn |
| Source status | WITHDRAWN |
| Market | — |
| Technology | Gas |
| Capacity | 49.0 MW |
| State | California |
| County | Stanislaus |
| Point of interconnection | Salado Substation 115 kV |
| Requested (queue) date | 2008-04-25 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | 2008-11-25 |
| Developer | — |
| Utility / transmission owner | PGAE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-29 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28
Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.