Wellsville 345 kV (AH1-699 - moved to TC2)

Wellsville 345 kV is a 58.0 MW gas interconnection project in Columbiana, Ohio with a current status of active.

58.0 MWCapacity
ActiveStatus
Market
GasTechnology

Project facts

Canonical nameWellsville 345 kV
Queue IDAH1-699 - moved to TC2
Statusactive
Source statusActive
Market
TechnologyGas
Capacity58.0 MW
StateOhio
CountyColumbiana
Point of interconnection
Requested (queue) date2025-04-04
Proposed in-service date
Operational date
Withdrawn date
Developer
Utility / transmission ownerATSI

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata