West Queue Project 221-A — Wind in Summit, Utah

West Queue Project 221-A — Wind in Summit, Utah is a 80.0 MW wind interconnection project in Summit, Utah with a current status of withdrawn. It is proposed to connect at Thief Creek - Evanston substations.

80.0 MWCapacity
WithdrawnStatus
WestMarket
WindTechnology

Project facts

Canonical nameWest Queue Project 221-A — Wind in Summit, Utah
Queue ID221-A
Statuswithdrawn
Source statuswithdrawn
MarketWest
TechnologyWind
Capacity80.0 MW
StateUtah
CountySummit
Point of interconnectionThief Creek - Evanston substations
Requested (queue) date2008-05-20
Proposed in-service date2010-12-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerPacifiCorp

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata