West Queue Project 235 — Geothermal in Millard, Utah

West Queue Project 235 — Geothermal in Millard, Utah is a 14.0 MW geothermal interconnection project in Millard, Utah with a current status of withdrawn. It is proposed to connect at Pole #75 on PacifiCorp's 46 kV Line Delta to Greymont.

14.0 MWCapacity
WithdrawnStatus
WestMarket
GeothermalTechnology

Project facts

Canonical nameWest Queue Project 235 — Geothermal in Millard, Utah
Queue ID235
Statuswithdrawn
Source statuswithdrawn
MarketWest
TechnologyGeothermal
Capacity14.0 MW
StateUtah
CountyMillard
Point of interconnectionPole #75 on PacifiCorp's 46 kV Line Delta to Greymont
Requested (queue) date2008-07-16
Proposed in-service date2009-08-30
Operational date
Withdrawn date
Developer
Utility / transmission ownerPacifiCorp

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.