West Queue Project 395 — Hydro in Deschutes, Oregon

West Queue Project 395 — Hydro in Deschutes, Oregon is a 1.6 MW hydro interconnection project in Deschutes, Oregon with a current status of withdrawn. It is proposed to connect at Circuit 5D243, Black Bear Feeder out of Shevlin Park substation.

1.6 MWCapacity
WithdrawnStatus
WestMarket
HydroTechnology

Project facts

Canonical nameWest Queue Project 395 — Hydro in Deschutes, Oregon
Queue ID395
Statuswithdrawn
Source statuswithdrawn
MarketWest
TechnologyHydro
Capacity1.6 MW
StateOregon
CountyDeschutes
Point of interconnectionCircuit 5D243, Black Bear Feeder out of Shevlin Park substation
Requested (queue) date2011-07-27
Proposed in-service date2013-10-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerPacifiCorp

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.