West Queue Project GI-2014-7 — Hydro in Clear Creek, Colorado

West Queue Project GI-2014-7 — Hydro in Clear Creek, Colorado is a 42.0 MW hydro interconnection project in Clear Creek, Colorado with a current status of active. It is proposed to connect at Cabin Creek Substation.

42.0 MWCapacity
ActiveStatus
WestMarket
HydroTechnology

Project facts

Canonical nameWest Queue Project GI-2014-7 — Hydro in Clear Creek, Colorado
Queue IDGI-2014-7
Statusactive
Source statusactive
MarketWest
TechnologyHydro
Capacity42.0 MW
StateColorado
CountyClear Creek
Point of interconnectionCabin Creek Substation
Requested (queue) date2014-07-31
Proposed in-service date2019-05-26
Operational date
Withdrawn date
Developer
Utility / transmission ownerPublic Service Company Of Colorado

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata