West Memphis-Genpower Keo 500kV Line Break (located at "CHALKBLUFFPV" 500kV POI SS, co-located with (J2431)

West Memphis-Genpower Keo 500kV Line Break (located at "CHALKBLUFFPV" 500kV POI SS, co-located with is a 150.0 MW battery interconnection project in St. Francis, Arkansas with a current status of withdrawn. It is proposed to connect at West Memphis-Genpower Keo 500kV Line Break (located at "CHALKBLUFFPV" 500kV POI SS, co-located with .

150.0 MWCapacity
WithdrawnStatus
—Market
BatteryTechnology

Project facts

Canonical nameWest Memphis-Genpower Keo 500kV Line Break (located at "CHALKBLUFFPV" 500kV POI SS, co-located with
Queue IDJ2431
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyBattery
Capacity150.0 MW
StateArkansas
CountySt. Francis
Point of interconnectionWest Memphis-Genpower Keo 500kV Line Break (located at "CHALKBLUFFPV" 500kV POI SS, co-located with
Requested (queue) date2022-09-13
Proposed in-service date2026-10-01
Operational date2026-10-01
Withdrawn date2025-07-30
Developer—
Utility / transmission ownerENTERGY ARKANSAS, LLC EATO

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-10-31phasePhase 2Phase 3low
2026-10-14phasePhase 1Phase 2low
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.