Weyerhaeuser TG#2 (GI-080)

Weyerhaeuser TG#2 is a 42.0 MW other interconnection project in Macon, Georgia with a current status of operational. It is proposed to connect at Weyerhaeuser 115 kV Sub.

42.0 MWCapacity
OperationalStatus
SoutheastMarket
OtherTechnology

Project facts

Canonical nameWeyerhaeuser TG#2
Queue IDGI-080
Statusoperational
Source statusoperational
MarketSoutheast
TechnologyOther
Capacity42.0 MW
StateGeorgia
CountyMacon
Point of interconnectionWeyerhaeuser 115 kV Sub
Requested (queue) date2023-12-31
Proposed in-service date
Operational date
Withdrawn date
Developer
Utility / transmission ownerGeorgia Transmission

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.