Wheatridge East Substation (G0362)

Wheatridge East Substation is a 204.0 MW wind interconnection project in Gilliam & Morrow, Oregon with a current status of operational. It is proposed to connect at New Substation near McNary 500 kV.

204.0 MWCapacity
OperationalStatus
ORMarket
WindTechnology

Project facts

Canonical nameWheatridge East Substation
Queue IDG0362
Statusoperational
Source statusENERGIZED
MarketOR
TechnologyWind
Capacity204.0 MW
StateOregon
CountyGilliam & Morrow
Point of interconnectionNew Substation near McNary 500 kV
Requested (queue) date2009-04-03
Proposed in-service date
Operational date2012-11-01
Withdrawn date
DeveloperWheatridge Wind Energy, LLC
Utility / transmission ownerBonneville Power Administration

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.