Whitins Pond Substation – NG Hopedale West Group Study (1307)

Whitins Pond Substation – NG Hopedale West Group Study is a 4.9 MW battery interconnection project in Worcester, Massachusetts with a current status of withdrawn. It is proposed to connect at NG Feeder 320W5, Whitins Pond T1.

4.9 MWCapacity
WithdrawnStatus
SEMAMarket
BatteryTechnology

Project facts

Canonical nameWhitins Pond Substation – NG Hopedale West Group Study
Queue ID1307
Statuswithdrawn
Source statusW
MarketSEMA
TechnologyBattery
Capacity4.9 MW
StateMassachusetts
CountyWorcester
Point of interconnectionNG Feeder 320W5, Whitins Pond T1
Requested (queue) date2022-09-09
Proposed in-service date2025-12-31
Operational date
Withdrawn date2025-06-13
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata