Willmar Municipal East Substation (57034_E04)

Willmar Municipal East Substation is a 2.0 MW other interconnection project in Kandiyohi, Minnesota with a current status of operational.

2.0 MWCapacity
OperationalStatus
MISOMarket
OtherTechnology

Project facts

Canonical nameWillmar Municipal East Substation
Queue ID57034_E04
Statusoperational
Source status(OP) Operating
MarketMISO
TechnologyOther
Capacity2.0 MW
StateMinnesota
CountyKandiyohi
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date2000-06-01
Withdrawn date—
Developer—
Utility / transmission ownerWillmar Municipal Utilities (MN)

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—operationalhigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata