WIT Ranch Wind (19INR0108)

WIT Ranch Wind is a 160.6 MW wind interconnection project with a current status of withdrawn. It is proposed to connect at 6050 Lake Pauline 138kV.

160.6 MWCapacity
WithdrawnStatus
ERCOTMarket
WindTechnology

Project facts

Canonical nameWIT Ranch Wind
Queue ID19INR0108
Statuswithdrawn
Source statuswithdrawn
MarketERCOT
TechnologyWind
Capacity160.6 MW
State
County
Point of interconnection6050 Lake Pauline 138kV
Requested (queue) date2017-08-09
Proposed in-service date2019-12-31
Operational date
Withdrawn date2018-11-06
DeveloperEon
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata