Wolf Creek - Blackberry 345 kV Tap (GEN-2022-054)

Wolf Creek - Blackberry 345 kV Tap is a 200.0 MW solar interconnection project in Bourbon, Kansas with a current status of active. It is proposed to connect at Wolf Creek - Blackberry 345 kV Tap.

200.0 MWCapacity
ActiveStatus
KSMarket
SolarTechnology

Project facts

Canonical nameWolf Creek - Blackberry 345 kV Tap
Queue IDGEN-2022-054
Statusactive
Source statusIA FULLY EXECUTED/ON SCHEDULE
MarketKS
TechnologySolar
Capacity200.0 MW
StateKansas
CountyBourbon
Point of interconnectionWolf Creek - Blackberry 345 kV Tap
Requested (queue) date2022-06-23
Proposed in-service date2029-12-31
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerNEET

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-11proposed_online_date2030-07-202029-12-31medium
2026-07-31new_project—activehigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.