Wolf Hollow I LP (55139_CTG2)

Wolf Hollow I LP is a 243.9 MW gas interconnection project in Hood, Texas with a current status of operational.

243.9 MWCapacity
OperationalStatus
ERCOMarket
GasTechnology

Project facts

Canonical nameWolf Hollow I LP
Queue ID55139_CTG2
Statusoperational
Source status(OP) Operating
MarketERCO
TechnologyGas
Capacity243.9 MW
StateTexas
CountyHood
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date2003-08-01
Withdrawn date—
Developer—
Utility / transmission ownerWolf Hollow I Power, LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_project—operationalhigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.